Site Records
RhydymwynThe Valley Works Rhydymwyn
Mold Clwyd North Wales
Site visit report: Valley works complex.
Photo: Entrance to Tunnel 2 (main entrance). Photo by Nick
Catford March 22nd 2001 saw 5 members of Sub Brit visit
the former chemical weapons and food storage buffer depot at Rhydymwyn in North
Wales. This visit was arranged with and fully sanctioned by the MAFF who own the site and we were met by 2 MAFF members of staff who would
escort us around the site with the local civilian security guards. Having duly
changed and collected hard hats and luminous safety jackets we started our tour
of the site. Starting from the guardhouse at the northern end of the site we walked down
the main road passing a number of buildings on both sides of us including P4
on our right. All these buildings were empty and had all the windows and doors
removed. It became obvious that the site is very overgrown in parts and is not
in use and hasn't been for several years. We passed a number of mounds and
our guides explained how these were buildings that had been demolished and grassed
over. There were a couple of shaft accesses from the site to the Milwr tunnel complex Halkin level but these have now been
capped. The access points had suffered collapses and the cavers involved had not
gained access into the Halkin level but had confirmed that it appeared that it
once existed. There is no access to these `shafts' that are now mounded over and
grassed. We continued along the road which turned right then left at which
point we came level with the northern access tunnel
into the underground complex. This tunnel now functions as the emergency escape
from the underground area. The blast doors have been removed and the entrance
bricked up. A single steel security door with heavy-duty locks now provides access
into this tunnel. Continuing along we reached the middle tunnel that is opposite
the gap between P5 and P6 buildings. This is now the main entrance into the underground complex and has 2 heavy-duty
steel security doors on it with the former blast door area being bricked up. Further
along the road on our right is the entrance to the southern
tunnel and this entrance is now sealed but has ventilation grills fitted high
up to assist airflow in the underground section. At this point the group split
in 2, as we were restricted to a maximum of 4 people at a time underground due
to health and safety requirements. Two Sub-Brit members and the 2 MAFF
officials went into the tunnels whilst the remaining 3 Sub-Brit members
headed to the southern end of the site to view the former filling rooms and the
old railway platforms. With the others going into the tunnels we continued along
the road through the site heading south. The River Alyn runs through a culvert
along the length of the site with a branch of it running underneath the tunnels
(more on this later). As we passed P6 and entered the southern part of the site
the road surface changed from concrete to Colas. This was to reduce the risk of
a spark from something being dropped onto the floor igniting one of the weapons
being filled. The filling rooms are small brick and concrete structures with roof
and wall vents and many have blast walls to protect the entrances. These buildings
still have their WW2 camouflage paint clearly visible
on then particularly on the east side which is protected from the weather. We
continued along the main path down to the southern boundary fence, which is topped
with barbed wire. Here the Alyn flows over what's left of the weir following the
floods last year and on to the Dee estuary. We turned and headed north walking
along the east path through the site. From this path we could see much more of
the paint on the side of the filling rooms and we entered all the buildings. One
of these had a sign reading 'cleanway to canteen' painted on the wall in excellent
condition. Many of these buildings are in a very poor state with leaking roofs
etc. Set in the middle of the filling rooms was the railway
platform. Again this was covered in Colas and we could clearly see where the
2 railway sidings used to be. Continuing North we walked along the edge of
the site and turned west back towards the main pathway when we reached the old
sewage works. These still had a lot of machinery in place but were very dilapidated.
Walking along the side of the sewage works our guides explained how in the
bad flooding last year the site became awash as the Alyn overflowed and a substantial
amount of flotsam and rubbish was washed onto the site. There were numerous piles
of this everywhere awaiting clearance. We crossed the end of the sewage works
and headed back towards the east fence and picked up the east path again. Continuing
North we passed the rear of P6 and at the gap between P5 and 6 crossed the site
back to the main tunnel entrance where the first party
were just emerging from the underground workings. Before entering the underground
workings we received a short but comprehensive safety briefing and collected our
emergency respirators. Large signs outside the entrance told us that the tunnels
were dangerous and empty. Our guide then led us into the tunnels. The
main entrance tunnel is around 250M long and is concrete
lined for the first half after which it is bare rock painted white. There is up
to 3 inches of water on the floor of this entrance tunnel. This
tunnel leads directly into chamber A that is transverse to the entrance tunnel.
At this point it is possible to go left, right or straight on into chambers B,C
and D.
We decide to turn right (north) and are standing
at the midpoint of chamber A. The chambers are all identical and have rough rock
walls painted white. Along the centre of this tunnel set into the floor are a
series of drain cover grills, which are all badly rusted, and we were warned not
to step on these as they would collapse under our bodyweight. There were various
puddles of water on the floor in this chamber. We could clearly hear the sound
of water running and this got louder the further north we headed. Reaching the
northern most point of chamber A we could look down the tunnel to the northern
door which was our emergency escape route. This tunnel was empty. Attached
to the walls high above our heads were the fixing points for the runners for the
long gone overhead cranes. There is no evidence of railway tracks in any of the
tunnels. We turned left and headed down a short piece of tunnel into chamber
B. Here we could see where the water noise was coming from. From a hole high
in the roof at the northern most point of chamber B a torrent of water was crashing
down onto the floor below. This was causing the puddles that were to be found
in various areas of the underground workings. We turned south and headed down
chamber B being careful not to tread in the grills set into the floor. We turned
right and moved into chamber C which had sluice channels cut into the floor along
each edge approximately 3 fete wide and 6 feet deep. The water tanks that stored
the Runcol (Mustard Gas) filled shells were located in chambers C & D and the
sluice channels were to remove water that leaked from the tanks into the drainage
system that was below the tunnels (more on that later). These sluices were now
filled with standing water and again the floor of these chambers was wet in places.
Moving into chamber D we moved to the northern end
where we viewed the way through to the air shafts. In order to access the shafts
it was necessary to cross a 6ft deep water pit. This used to be the way down into
the drainage system beneath the underground chambers. The whole system was run
by pumps that got rid of the excess water and the drains were up to 5ft tall in
places. The pumps were switched off many years ago and these have now become flooded
and access to them is not possible unless you have a wetsuit and breathing apparatus!
We continued south along chamber D and at the far end was the southern vent
shaft access, which was identical to the northern one. We crossed back into
chamber C and then worked our way back to chamber B and eventually A. In some
of the chambers the consulting mine engineers employed by the MAFF
have places measurements to check for shifting of materials in the chambers and
this has resulted in loose rock being removed in a couple of places and a small
amount of re-inforcing being put in at the southern vent shaft access. We walked
back to the main entrance tunnel and exited stopping to look at 2 vehicle gates
that were rusted to the walls. These obviously provided an 'air lock' type gate
for allowing vehicles in and out or the workings. We emerged into the sunshine
to be greeted by the 2nd Sub-Brit party making their way back towards us
having toured the south of the site. We then all set off together to tour the
rest of the site. We walked back across to the east path and continued along stopping
to look in all buildings of interest. Building P5 used to house flour as part
of the MAFF buffer stock and directly
behind P5 is one of the sheds that used to house the shunter engines. There is
a small amount of standard gauge track set into the floor outside P5 on its west
side. Continuing along we then visited the quality control labs where there
were a number of yellow squares in the floor marked 'toxic drain'. In these buildings
which again had no windows or doors there were remains of light fittings and a
number of power junction boxes on the walls. We left the labs and walked across
the north end of the site passing the old powerhouse and garages that house an
ambulance and fire engine arriving back at the gatehouse. Throughout the site
there are numerous boreholes that the MAFF use for monitoring whether there is
any leakage from the significant number of toxic waste burial pits which are marked and fenced off
on the site. The site is a mile long and is totally disused the only presence
being security guards from Citex who are contracted to the MAFF to provide site security.
No restrictions whatsoever were placed on us by the MAFF and we extensively photographed
and video'd the site and the underground workings. I would like to take this
opportunity to thank the MAFF for their extensive co-operation
and allowing us to visit this important site. Many of the buildings on the
site were demolished early in 2003. Some works are being done at the foot of the
bank adjacent to the tunnel entrances to stabilise the bank where some small buildings
have been demolished, at the southern end of the site a new bank has been built
to replace the washed out river bank, this is stone faced and has new boundary
fencing to close the gap in the original boundary. See last two photographs in
the gallery.
A
short History of` The Valley Works' is available here. Home Page Last updated 7th March 2003
© 1997-2008 Subterranea Britannica |